Our official representative shared an excellent photo and video report on the work carried out in the Samara Region. This time, materials from the "Bronya" line successfully solved the task of thermal insulation of the vestibule of a private house in the village of Yagodnoye.
The customer's main goal was to prevent freezing of the walls during the cold season, while a critically important condition was to preserve the usable space inside the room. That is why the choice fell on ultra-thin "Bronya" thermal insulation — an ideal modern solution when every centimeter of area counts.
The work was carried out in stages and in strict accordance with the technology:
-
Initially, the concrete wall surface was thoroughly dedusted and treated with a deep-penetration primer.
-
Then, using a spatula, the craftsmen applied two layers of ultra-thin "Bronya Facade" thermal insulation (1 mm per layer).
-
The finishing stage was the application of one layer of the "Bronya Light" modification with a thickness of 1 mm.
Each layer was applied with strict adherence to the mandatory interlayer drying time of 24 hours.
As a result, the total thickness of the thermal insulation coating was only 3 mm! The photographs from the site show that the material lays down in an even, neat layer. When following the instructions, the application process of our ultra-thin thermal insulation is so simple and convenient that it causes absolutely no discomfort during work. Working with the material allows craftsmen to maintain an excellent positive mood, which was reflected on the site in the form of a drawing on the wall made from our thermal insulation.
The result is natural: reliable thermal protection is ensured, the useful area of the vestibule is fully preserved, and the customer, as always, remains completely satisfied with the result.